LAHORE: The National Transmission and Dispatch Company (NTDC) is completing its ongoing projects on a fast track with the best utilization of resources despite the COVID-19 pandemic.

In a recent development, the construction of 38 kilometer long 500 kV double circuit quad bundle transmission line consists of 126 towers for looping in & out 500 kV Single Circuit, Haveli Bahadur Shah-Gatti Circuit-II at 500 kV Grid Station Faisalabad West, has been successfully energized on load on 22 May 2020.

Managing Director NTDC Engr Dr. Khawaja Riffat Hassan has appreciated the efforts of NTDC teams for completing both these tasks by working day and night during coronavirus pandemic.

The NTDC spokesman has said that the transmission line is transmitting power from Haveli Bahadur Shah power plant to 500 kV grid station Gatti (Faisalabad) via under construction 500 kV Grid Station Faisalabad West.