ISLAMABAD: The Independent System and Market Operator (ISMO) has cautioned the government against committing to unnecessary new electricity generation capacity over the next decade, warning that rapid expansion of distributed solar generation, uncertain electricity demand and changing consumption patterns could leave power plants underutilised and further increase capacity payments per unit of electricity supplied to consumers, reliable sources in NEPRA told Business Recorder.
In its revised 166-page Integrated System Plan (ISP) 2026–36, prepared jointly with the National Grid Company of Pakistan (National Grid), ISMO has identified a fundamental transformation in Pakistan’s electricity consumption pattern, arguing that the country’s principal power-sector challenge is gradually shifting from generation adequacy towards system flexibility, transmission constraints and the integration of renewable energy.
The plan projects that gross electricity demand will increase by an average of 3 percent annually through FY2036. However, net electricity supplied through the national grid is expected to grow by only 1.75 per cent annually, as an increasing proportion of electricity consumption is being met through distributed solar photovoltaic (PV) installations.
At the same time, peak demand is projected to increase from 26,768MW in FY2025 to 35,127MW by FY2036 under the Reference Scenario, representing average annual growth of approximately 2.5 per cent.
This divergence between electricity consumption and grid demand is creating a difficult financial and operational situation for the power sector. While consumers increasingly generate electricity through rooftop and other distributed solar installations during daylight hours, the national grid must retain sufficient generation capacity to meet demand during evening and night-time hours when solar generation becomes unavailable.
Consequently, the electricity system is experiencing lower utilisation of existing generation assets, a declining load factor and a growing requirement for flexible generation, battery storage and improved demand management.
ISMO has; therefore, recommended that the government exercise caution before approving additional generation projects and ensure that future investments are supported by realistic demand forecasts and least-cost optimisation.
The plan estimates that Pakistan’s installed generation capacity will increase from approximately 39,141MW in FY2026 to 52,527MW by FY2036 under the Reference Scenario. This expansion includes 8,664MW of already committed capacity and another 7,942MW of capacity optimised through the planning exercise, against retirement of 3,219MW of existing generation capacity.
Significantly, the optimisation exercise has not selected any new fossil-fuel or imported-fuel-based power plant under any of the three demand scenarios considered by ISMO.
The organisation has instead proposed greater reliance on hydropower, nuclear energy, solar and wind generation, alongside battery energy storage systems (BESS), to manage the changing electricity demand profile.
The total present value of generation expansion costs under the Reference Scenario has been estimated at approximately USD44.2 billion, compared with USD41.6 billion under the Low Demand Scenario and USD50.7 billion under the High Demand Scenario.
The report; however, makes it clear that its recommendations are indicative and do not create an obligation to procure electricity from any project included or optimised in the plan. Decisions concerning procurement, project development, tariffs and dispatch remain with the competent authorities under applicable laws and regulations.
One of the most important findings of the ISP concerns the rapid growth of distributed solar generation and its impact on the economics of Pakistan’s national electricity system.
According to ISMO, installed generation capacity stood at 38,941MW in June 2026. Renewable energy sources, including hydropower, grid-scale solar, wind and bagasse, accounted for approximately 38 per cent of installed capacity, while thermal and nuclear generation represented the remaining 62 per cent.
During FY2026, the generation fleet produced 133,911GWh of electricity. Thermal power plants contributed 48 per cent, hydropower 30 per cent, nuclear generation 17 per cent and other renewable sources 5 per cent. However, grid-based electricity generation has declined considerably from its previous peak.
The report states that grid-based generation fell by nearly 13 per cent from 154 terawatt-hours (TWh) in FY2022 to approximately 134TWh in FY2026, mainly because of the rapid expansion of distributed solar photovoltaic installations.
In contrast, peak demand has continued to increase. It reached 27,169MW in FY2026, approximately 40 per cent higher than the peak recorded in FY2016.
This trend demonstrates that distributed solar is reducing electricity purchases from the national grid during daylight hours but is not eliminating the requirement for grid electricity during the evening peak.
ISMO has identified the declining system load factor as a major consequence of this changing consumption pattern. The load factor declined from 67 per cent in FY2016 to 58 per cent in FY2026, indicating that peak demand is increasing more rapidly than total electricity consumption.
The decline in load factor has serious financial implications because generation capacity is maintained to meet the highest demand even when a substantial portion of that capacity remains unused during most hours of the year. Consequently, fixed generation costs are recovered through a smaller volume of electricity supplied by the grid, increasing the capacity price payable per unit of electricity consumed.
The report notes that this trend could further aggravate the existing financial difficulties of the power sector if additional generation capacity is approved without adequately considering the changing demand profile. The situation is particularly concerning because the highest demand occurs for a relatively short period.
ISMO’s analysis indicates that electricity demand within 1,000MW of the annual peak remained for only 31 hours during FY2026, equivalent to approximately 0.35 per cent of the year. Similarly, demand within 2,000MW of the annual peak occurred for 159 hours during FY2026.
The corresponding duration of the 1,000MW peak band was only eight hours in FY2024, although it subsequently increased to 23 hours in FY2025 and 31 hours in FY2026.
According to ISMO, the peak demand is largely seasonal and driven by space-cooling requirements, particularly during summer.
The organisation has linked this situation to energy-inefficient buildings and the concentration of electricity consumption during a limited number of hours.
Maintaining expensive generation capacity merely to meet such short-lived peaks could; therefore, increase the financial burden on consumers without providing proportionate benefits.
ISMO has argued that demand-side management, including time-of-use tariffs, energy efficiency, demand response and improved load management, would be a more economical approach than immediately investing in additional peaking power plants.
The ISP 2026 has considered three electricity demand scenarios: Low, Medium and High.
The Medium Demand Scenario has been adopted as the Reference Scenario because ISMO considers it the most probable outcome for the planning period.
Under this scenario, gross electricity demand is projected to increase by 3 per cent annually through FY2036, while net energy supplied through the grid is expected to increase by only 1.75 per cent annually.
Net electricity demand supplied by the grid is projected to reach 166,406GWh in FY2036. Net peak demand is expected to increase from 26,768MW in FY2025 to 35,127MW in FY2036.
Under the Low Demand Scenario, net peak demand is projected to reach 32,965MW by FY2036, while under the High Demand Scenario it could increase to 43,765MW.
These differences demonstrate the risks associated with committing to long-term generation investments based on uncertain economic growth and electricity consumption projections.
ISMO has cautioned that if demand follows the lower trajectory, power plants developed under the Reference Scenario could remain underutilised, resulting in higher capacity payments per unit of electricity supplied. Conversely, substantially higher demand would require additional generation capacity, particularly from wind and solar resources.
The High Demand Scenario envisages significantly greater renewable energy additions, including 6,262MW of solar photovoltaic capacity and 8,342MW of wind generation through optimisation.
However, ISMO has specifically clarified that the High Demand Scenario has been modelled for compliance purposes and should not form the basis of any capacity commitment.
The organisation has recommended continuously monitoring changes in economic conditions, electricity consumption and distributed energy resources before revising the generation expansion programme. It has also proposed improving the quality of demand forecasting by obtaining more reliable and timely information from distribution companies, K-Electric and other stakeholders.
Under the Reference Scenario, Pakistan’s installed generation capacity is projected to increase from approximately 39,141MW in FY2026 to 52,527MW by FY2036.
The plan identifies 8,664MW of committed capacity additions, comprising 5,195MW of hydropower, 1,000MW of cross-border electricity supply, 2,439MW of market-based wind and solar projects and a 30MW residual fuel oil-based power plant in Gwadar.
In addition to these committed projects, ISMO has optimised 7,942MW of new generation capacity to meet projected electricity requirements. At the same time, 3,219MW of existing residual fuel oil, local natural gas and RLNG-based generation capacity is scheduled for retirement during the planning period.
The expansion programme is divided into two distinct phases.
During the initial period up to FY2031, only 918MW of additional capacity has been selected through optimisation. These projects are concentrated in the K-Electric and Makran-Gwadar regions. More than 80 per cent of the optimised capacity is scheduled for commissioning after FY2031.
The major projects include the 1,200MW Chashma-5 nuclear power plant, scheduled for FY2032, and the 4,500MW Diamer Bhasha hydropower project, planned in three 1,500MW phases between FY2033 and FY2035. Another 644MW of solar photovoltaic capacity and 73MW of wind generation have been optimised for FY2036.
The report’s generation expansion strategy reflects a clear preference for indigenous energy resources and a gradual reduction in dependence on imported fuels.
No additional fossil-fuel-based generation capacity has been selected through the optimisation process in any of the three demand scenarios.
The plan indicates that existing thermal power plants will continue to play a role in meeting electricity requirements, but their overall contribution will decline as hydropower, nuclear and renewable generation increase.
The treatment of the Diamer Bhasha hydropower project is another significant feature of the ISP. Although the entire 4,500MW project has been included as a strategic investment in the generation expansion programme, only its first 1,500MW tranche has been selected on a least-cost basis. The remaining 3,000MW has been included with a Least Cost Violation (LCV) of USD3.91 billion, which, according to ISMO, is to be borne by the project sponsor.
This distinction is important because the inclusion of a strategic project in the expansion plan does not necessarily mean that its entire capacity represents the least-cost option for electricity consumers.
ISMO has applied the least-cost optimisation framework to identify the most economical generation expansion pathway while recognising the strategic importance of certain projects.
The organisation has also recommended that the cost of projects should be closely monitored and that unjustified cost overruns resulting from implementation delays should not be passed on to electricity consumers.
The plan proposes that the project sponsor should bear the financial consequences of delays and additional costs where these are not justified. The proposed Chashma-5 nuclear power plant, with a capacity of 1,200MW, has been selected on a least-cost basis in all three demand scenarios. Similarly, a 269MW hybrid wind-solar project has been selected in all scenarios.
The principal differences between the three scenarios relate to the amount and location of additional solar and wind generation.
The electricity generation mix is expected to undergo a substantial transformation during the planning period. The share of renewable generation, including large hydropower, is projected to increase from approximately 36 per cent in FY2027 to 62 per cent by FY2036.
Hydropower will remain the largest renewable source, with generation expected to increase to approximately 84TWh by FY2036, almost twice the existing level.
Wind generation is projected to contribute approximately 7 per cent of electricity supplied through the grid, while solar photovoltaic generation will account for around 4 per cent and bagasse approximately 1 per cent.
Nuclear generation is expected to contribute around 20 per cent of electricity demand by FY2036. In contrast, conventional thermal generation is projected to decline to approximately 15 per cent of total electricity supplied.
The reduction will primarily be reflected in lower dispatch of RLNG-based and imported coal-fired power plants.
The report indicates that the increasing contribution of indigenous hydropower and renewable energy could reduce the country’s exposure to imported fuel prices and foreign exchange fluctuations. However, the increasing share of variable renewable generation will also create operational challenges for the national grid.
Solar and wind generation are dependent on weather conditions and cannot always be dispatched according to system requirements.
The power system will therefore require greater flexibility to accommodate fluctuations in renewable generation and maintain the required level of frequency and voltage stability.
ISMO has identified battery energy storage as a critical component of Pakistan’s future electricity system. The report proposes adding 1,740MW of Battery Energy Storage Systems by FY2036 to address the steep evening demand increase, improve frequency regulation and provide operational flexibility.
The proposed deployment comprises 1,000MW of battery storage on the National Grid system in two 500MW phases, which are required to be commissioned by March 2029.
Another 300MW is proposed for the K-Electric system, to be deployed in phases between FY2029 and FY2032.
The plan also includes 360MW of battery storage for Gwadar and 80MW through bilateral contracts in the wholesale electricity market.
The proposed storage capacity is intended to help the system manage the mismatch between daytime solar generation and evening electricity consumption.
During daylight hours, distributed and grid-scale solar generation can significantly reduce demand from conventional power plants.
However, as solar generation declines after sunset, electricity demand must increasingly be met through conventional generation, imports, hydropower and other available resources.
This creates a steep evening ramp that existing thermal power plants may not be able to follow because of their technical limitations and restrictions on start-stop operations. Battery storage can absorb electricity during periods of lower demand or excess renewable generation and release it when the system requires additional supply.
ISMO has also highlighted the importance of battery storage for frequency regulation.
According to the transmission studies, during March minimum-load conditions, the loss of the largest generating unit could cause system frequency to fall below the Grid Code limit of 49.3Hz without the planned battery storage.
With the proposed BESS facilities, the system is expected to comply with the applicable frequency requirement under the studied conditions.
The report recommends a phased approach rather than immediately committing to the entire potential storage requirement.
Initially, the minimum essential battery capacity should be installed, particularly the 1,000MW/2,000MWh proposed for the National Grid system by March 2029.
Any additional deployment should be determined after detailed studies of power dispatch, thermal plant flexibility, time-of-use tariffs and demand-side management opportunities.
The organisation has also recommended evaluating battery storage at the distribution-company level, where it could help improve local network management and integrate distributed energy resources.
ISMO has proposed developing a national Demand-Side Management (DSM) strategy to reduce the need for expensive new generation capacity.
The proposed strategy will cover energy efficiency, demand response, load management and better utilisation of distributed energy resources.
A dedicated DSM team within ISMO will lead the process and develop the necessary policy, regulatory and institutional framework.
The organisation has recommended launching pilot programmes before introducing a nationwide mechanism.
The potential contribution of demand-side measures will subsequently be incorporated into future iterations of the Indicative Generation Capacity Expansion Plan (IGCEP).
The report argues that demand-side management should be treated as an alternative to new peaking generation capacity during the planning process.
Time-of-use tariffs could encourage consumers to shift electricity consumption away from peak hours, while demand-response programmes could provide incentives for large consumers to reduce or adjust their consumption when the power system is under stress.
Energy efficiency improvements in buildings could also reduce the seasonal cooling load that is primarily responsible for the sharp increase in electricity demand during summer.
ISMO believes that such measures could help improve the system load factor and increase utilisation of existing generation assets.
Another major component of the plan concerns the electricity supply arrangement between the National Grid and K-Electric.
ISMO has identified the enhancement of the interconnection between the two systems as the only candidate transmission line selected through the generation expansion optimisation process. The existing transfer capability from the National Grid to K-Electric stands at approximately 2,050MW. This is projected to increase to 3,263MW by FY2036, representing an additional transfer capability of approximately 1,200MW.
The proposed enhancement is intended to enable K-Electric to import greater quantities of relatively inexpensive electricity from the national grid and reduce dependence on expensive imported-fuel-based generation.
The report indicates that additional renewable energy capacity in the K-Electric system has also been considered because the existing interconnection capacity limits the amount of lower-cost electricity that can be imported from the National Grid.
The generation optimisation exercise has selected a 269MW hybrid wind-solar project and 556MW of wind capacity in the K-Electric region during the earlier years of the planning period.
The report has stressed that the proposed interconnection scheme needs to be finalised in consultation with K-Electric’s consultant.
It has recommended treating the enhancement as a priority project and bringing it into service at the earliest possible date.
The improvement is expected to provide greater flexibility in electricity dispatch and reduce the overall cost of supplying electricity to Karachi.
ISMO has separately highlighted the electricity supply challenges faced by the Makran-Gwadar region. The area currently receives electricity through the 132kV National Grid-Makran transmission corridor and international interconnections with Iran. However, the existing transmission corridor is constrained by its length and voltage regulation requirements, while electricity imports from Iran have remained subject to interruptions.
The report proposes a 30MW firm generation project accompanied by a 30MW/ 30MWh battery energy storage facility to address immediate reliability requirements. It also identifies the possibility of developing additional solar photovoltaic capacity and battery storage in the region.
However, ISMO has recommended that these investments should be made in phases and only after actual demand growth is confirmed.
The plan includes optimisation of up to 695MW of solar photovoltaic capacity and 330MW/1,320MWh of battery storage for Gwadar under the relevant planning assessment.
ISMO has cautioned against committing to the full capacity immediately because the future electricity demand of the region remains uncertain.
It has recommended assessing the wind energy potential of the area and reviewing the reliability, price and contractual arrangements governing electricity imports from Iran.
The organisation believes that the initial reliability-enhancement solution should be implemented first, with additional generation and storage investments considered after monitoring actual consumption patterns.
The ISP has placed considerable emphasis on strengthening Pakistan’s transmission infrastructure, arguing that timely completion of transmission projects will be essential for evacuating electricity from upcoming hydropower and renewable energy projects.
The Transmission System Expansion Plan 2026 has been developed in accordance with the generation expansion programme and spatial demand forecasts of distribution companies.
ISMO and National Grid have undertaken load-flow, short-circuit and transient-stability studies for FY2029, FY2031 and FY2036 under summer, winter and minimum-load conditions.
According to the plan, the proposed transmission expansion and reinforcement projects enable the network to meet Grid Code requirements under normal and N-1 operating conditions for the studied years.
The estimated cost of under-construction transmission projects stands at USD3.297 billion, while planned projects identified in the transmission expansion programme carry an estimated cost of USD5.879 billion.
The combined estimated investment is approximately USD9.176 billion.
These estimates cover connection facilities for new generation projects, transmission reinforcements required to transfer electricity to load centres and expansion of transformation capacity.
One of the most important priorities is the completion of the Islamabad West grid station and associated 500kV transmission lines connecting Ghazi Brotha, Islamabad West, Ludewala and Faisalabad West.
ISMO has warned that delays in these projects could prevent the evacuation of a substantial portion of upcoming hydropower generation.
The organisation has also recommended expediting reactive power compensation equipment, including STATCOMs, bus reactors and switched shunt capacitors.
These facilities are required to manage voltage fluctuations, particularly during periods of low electricity demand when distributed solar generation reduces conventional generation on the grid.
The increasing contribution of distributed solar generation is also creating challenges for the stability of the transmission system.
ISMO has observed that the growing number of solar installations, combined with fewer conventional generating units operating during low-demand periods, is reducing system short-circuit strength.
The report identifies a particular concern at the Lahore high-voltage direct-current (HVDC) converter, where the short-circuit ratio could fall below 3 under low-demand conditions.
The organisation has recommended evaluating the use of retired or retiring power plants as synchronous condensers to strengthen the grid.
Synchronous condensers can provide reactive power support and improve voltage stability without operating as conventional electricity-generating units.
The report has also emphasised the need for improved dynamic modelling, system monitoring and standardisation of equipment ratings and substation designs.
These measures are considered important for maintaining the reliability of the transmission network as the share of variable renewable energy increases.
Despite the challenges associated with renewable energy integration, ISMO’s Reference Scenario indicates that Pakistan’s generation capacity will remain adequate throughout the planning period.
After accounting for machine derating, planned and forced outages, hydrological variations and the variability of wind and solar generation, the reserve margin is projected to increase from 6 per cent in FY2027 to 10 per cent in FY2028.
It is expected to rise to approximately 17 per cent in FY2029 and remain between 20 and 22 per cent during FY2031–FY2035. The reserve margin is projected to settle at approximately 18 per cent in FY2036.
The report has clarified that installed capacity represents the maximum nameplate capacity of generating plants and does not necessarily reflect the electricity that can be delivered at any given time.
Actual generation capability is affected by equipment derating, outages, seasonal hydrology and renewable energy availability.
ISMO’s assessment indicates that the available generation capability will remain above projected peak demand in every year of the Reference Scenario.
However, the organisation has stressed that adequate generation capacity alone will not ensure a reliable electricity system.
The increasing need for flexibility, particularly during low-demand and evening peak periods, will require battery storage, improved thermal operations and transmission reinforcements.
The plan has identified delays in committed and strategic generation projects as another major threat to the future power system.
The expansion programme relies heavily on large hydropower projects, including Dasu, Mohmand and Diamer Bhasha.
ISMO has warned that delays in these projects could affect generation adequacy, electricity dispatch and transmission loading, particularly on the South-to-North transmission interface.
Delays could also increase project costs and create additional pressure on electricity tariffs.
The organisation has recommended fixing commissioning dates based on the data cut-off date, verifying implementation progress through documentary evidence and ensuring that unjustified cost overruns are not transferred to electricity consumers.
It has also proposed that future projects should not automatically be treated as committed merely because they have been announced or included in an earlier planning exercise.
Instead, projects should undergo optimisation through the IGCEP process and achieve clearly defined implementation milestones before being assigned committed status.
This recommendation is particularly relevant given the substantial financial consequences of long-term power purchase commitments.
Although the proposed generation mix is expected to reduce dependence on imported fuels, ISMO has acknowledged that Pakistan will continue to face exposure to international fuel prices and exchange-rate movements.
The cost of operating the remaining imported-fuel-based power plants will remain sensitive to changes in the prices of RLNG, imported coal and other energy commodities.
Similarly, delays in generation and transmission projects could increase financing and construction costs.
The plan has also highlighted the need to improve the accuracy and timeliness of information provided by power-sector entities.
ISMO has relied on information furnished by NEPRA, the Ministry of Planning, the State Bank of Pakistan, the Finance Division, PPIB, CPPA-G, PPMC, NEECA, K-Electric, WAPDA, National Grid, GENCOs and distribution companies, among other institutions.
The organisation has acknowledged that electricity demand forecasts are inherently uncertain and actual outcomes may differ from the assumptions used in the plan.
It has therefore proposed continuous monitoring and periodic revisions as economic conditions, costs, technology and government policies evolve.
ISMO has also outlined recommendations for NEPRA, procurement agencies, project sponsors and other power-sector stakeholders.
The organisation has emphasised that future capacity additions should be based on least-cost optimisation and realistic demand projections.
It has recommended that NEPRA ensure the capital and operating costs approved for projects do not exceed the costs assumed during the generation expansion optimisation process without proper justification.
Where the regulator determines higher costs, the relevant project should undergo a fresh assessment before tariff determination or approval.
The report has also recommended that transmission costs associated with candidate generation projects should be assessed through an appropriate cost-allocation framework.
At present, the transmission costs of candidate generation projects are indicative, pending approval of the relevant framework by the competent forum.
This is important because the cost of connecting new generation projects to the national grid can materially affect their overall economic viability and ranking in the least-cost optimisation process.
ISMO has further recommended that the minimum essential battery storage capacity should be deployed first, with additional storage investments linked to detailed operational assessments.
It has also called for expediting the National Grid-K-Electric interconnection, completing critical northern transmission reinforcements and developing a comprehensive demand-side management strategy.
Power sector faces a transition from capacity expansion to system flexibility.
The Integrated System Plan 2026–36 presents a significant change in the approach to Pakistan’s long-term electricity planning.
For years, the power-sector debate has largely focused on adding generation capacity to address shortages and meet increasing electricity demand. However, ISMO’s latest assessment suggests that simply adding more power plants may no longer be the most economical response to the country’s emerging electricity requirements.
The rapid expansion of distributed solar generation is reducing the volume of electricity purchased from the national grid, while the requirement to meet evening peak demand remains high.
This is increasing the cost of maintaining generation capacity and creating a mismatch between the operational characteristics of conventional thermal plants and the changing demand profile.
The plan; therefore, places greater emphasis on battery storage, demand-side management, transmission infrastructure and the efficient use of existing generation assets.
Its financial implications are particularly important for Pakistan, where consumers continue to face high electricity tariffs and the power sector remains under pressure from fixed capacity costs.
If additional generation projects are approved without sufficient demand justification, the resulting under-utilisation could further increase the capacity price recovered through electricity tariffs.
On the other hand, delays in hydropower projects, transmission reinforcements and battery storage could create operational constraints even where sufficient installed generation capacity exists.
The plan’s estimated USD44.2 billion present value of generation expansion costs under the Reference Scenario together with approximately USD9.176 billion in identified ongoing and planned transmission investments underscore the scale of financial commitments involved in restructuring the power system.
However, these estimates should not be interpreted as a single immediately payable investment requirement. The generation expansion and transmission investment estimates cover different components and planning periods, while actual procurement, financing, implementation and regulatory approvals remain subject to decisions by the competent authorities.
The central recommendation emerging from the ISP is that Pakistan should avoid unnecessary generation commitments, improve the utilisation of existing power plants, accelerate investments in essential transmission infrastructure and introduce storage and demand-management solutions in a phased manner.
ISMO has also made it clear that the plan will need to be updated as electricity demand, economic growth, fuel prices, exchange rates and distributed energy installations evolve.
The organisation’s overall assessment is that Pakistan’s future electricity challenge will not simply be about generating more power. It will increasingly be about ensuring that electricity is available at the right time, at the right location and at the lowest possible cost, without imposing additional financial burdens on consumers. MUSHTAQ GHUMMAN